Oakland Airport

Oakland Airport 28-L Runway/ Desilva Gates Construction

$1.2 Million

Oakland International Airport – Oakland, CA

  • Perform ASTM E950 Profilograph Testing
  • Provide consulting regarding surface tolerance specification for the project
  • Provide profile diamond grinding to correct out-of-tolerance defects on the runway
  • Provide transverse grooving to improve runway drainage and increase surface friction

Contractor

Project Details

  • Obtained and provided comprehensive analysis of surface smoothness data and consulted with the contractor regarding solutions to correct deficiencies above allowable tolerances per specification.
  • Utilized and deployed our experienced team and extensive fleet of equipment to successfully complete 102,000 square yards of transverse runway grooving within 5 days, requiring creative and precise planning to meet production goals during a 24-hour, 5-day working window.